Change-over time reduction and stock organisation in a truck cooler assembly line

784 visningar
uppladdat: 2004-01-01
Inactive member

Inactive member

Nedanstående innehåll är skapat av Mimers Brunns besökare. Kommentera arbete
Valeo Engine Cooling in Mjällby mainly produces truck coolers. At the production site, there is on-going work to phase out the automobile cooler manufacturing and concentrate the production to one facility. At the same time the main production flow needs to be improved. The purpose of this Master's Thesis is to analyze the flow of coolers from the brazing furnaces through the different crimping and welding assembly stations, to find problem areas and implement changes to improve the situation. The analysis has pointed out three different areas:
  • The need to increase throughput of the brazing furnaces and lower the work in progress levels by reducing change-over times
  • The necessity to organize the crimping stock in FIFO and improve the layout
  • The importance of having a separate stock area assigned for manual welding assembly
Currently, the brazing furnaces are operated 24 hours a day and this is still not sufficient to meet customer demands. Therefore, every extra hour of production that can be gained is valuable. The work with the change-overs in the brazing furnaces has resulted in a step-by-step guide to shorten the change-over time. It is based on the SMED methodology (Single Digit Minute Exchange of Die) and an analysis of shift reports from the furnaces. The yearly extra profit that would be made by implementing each step has been calculated to be between 2 and approximately 15 million SEK. The work is supposed to point out the importance of working on reducing the change-over times and show which actions are the most profitable. The actions include: reducing the number of belt speeds in the furnaces, having an end of line stock for all products, optimizing change-overs on the same belt speed and shorten the time used for changing belt speeds. Today, the crimping storage is very unorganized and difficult to overview. The plan is to store the cores in rows of wagons, instead of pallets, and to use the FIFO (First In First Out) principle. The stock levels fluctuate heavily over the week. To be able to dimension the new storage area the variations have been carefully analyzed. Two layout suggestions were created and compared. Both alternatives have advantages, but one of them was found to be superior due to higher safety and better stock organisation. The layout of a nearby water leak test station had to be changed in order to have the cell working as efficiently as today. The final layout alternative made this possible using a smaller area than today. The analysis of the main process flow showed that today there is no separate storage area for manual welding. Instead, these products are mixed within the robot welding assembly stock, and thereby complicating the work for the operators. A new storage area was needed with an area able to store 15 pallets. From the decision factors two layout alternatives were created. The chosen alternative is located closer to the manual welding cells and requires less extensive layout changes. To have everything working on the least possible area, the supply of tanks to a nearby crimping station had to be done with supply trains. These wagons were ...

...läs fortsättningen genom att logga in dig.

Medlemskap krävs

För att komma åt allt innehåll på Mimers Brunn måste du vara medlem och inloggad.
Kontot skapar du endast via facebook.

Källor för arbetet

Saknas

Kommentera arbetet: Change-over time reduction and stock organisation in a truck cooler assembly line

 
Tack för din kommentar! Ladda om sidan för att se den. ×
Det verkar som att du glömde skriva något ×
Du måste vara inloggad för att kunna kommentera. ×
Något verkar ha gått fel med din kommentar, försök igen! ×

Kommentarer på arbetet

Inga kommentarer än :(

Källhänvisning

Inactive member [2004-01-01]   Change-over time reduction and stock organisation in a truck cooler assembly line
Mimers Brunn [Online]. https://mimersbrunn.se/article?id=53753 [2024-04-29]

Rapportera det här arbetet

Är det något du ogillar med arbetet? Rapportera
Vad är problemet?



Mimers Brunns personal granskar flaggade arbeten kontinuerligt för att upptäcka om något strider mot riktlinjerna för webbplatsen. Arbeten som inte följer riktlinjerna tas bort och upprepade överträdelser kan leda till att användarens konto avslutas.
Din rapportering har mottagits, tack så mycket. ×
Du måste vara inloggad för att kunna rapportera arbeten. ×
Något verkar ha gått fel med din rapportering, försök igen. ×
Det verkar som om du har glömt något att specificera ×
Du har redan rapporterat det här arbetet. Vi gör vårt bästa för att så snabbt som möjligt granska arbetet. ×